The ACP Team is grateful to God for His faithfulness for the Cathedral Building project. Over the last two years we were able to continue with works (in Lots) under Phase 3 despite the challenges arising from the COVID-19 Pandemic. We made significant progress on wall finishes (plastering) and external works for storm water drainage, paving, boundary fencing and gates, among other improvements. Thank you, for your continued support.

Kampala Diocese is celebrating its 50th Anniversary this year! We bless the Lord for His Ministry. The desire of the Diocese is to hold the celebrations in the new sanctuary. The ACP team together with the Cathedral leadership, the Consultants and Contractors are working to ensure that the site will be in usable state to host the events as desired with the help of God. Brethren, the finishing line is near, do not despair! We encourage you to continue to: Pray, Participate, Provide and (mobilize) Partners for this great work as we honour God.

A. Financial Status

 

ACP Summary of Collections for the week 2nd to 9th May, 2022.

8am service UGX. 2,092,000/=
10:00am service UGX. 3,749,000/= USD 1,000
12:00 Noon serviceUGX. 2,281,000/=
Baptism ServiceUGX. 7,913,000/= USD 4
Office/Walk in CollectionsUGX. 4,591,500/=
Total CollectionsUGX. 20,626,500/= ; USD $ 1,004

Cash fixed for Selected Works – 1,837,242,966/=

Cash at hand by 9 th May, 2022- 914,290,573/=

B. Technical Status

Effective April 2022, the project Consultants have been re-engaged in line with the statutory requirements under the Building Control Regulations. The following works are currently on-going:

Lot 5A – Public Washrooms (re-located) and Selected offices on Lower Ground

• Lot 6A – Floor Finishes in Terrazzo (for high traffic and wet areas)

• Lot 8A – Windows to Vertical Walls

A contractor for Lot 9 – Acoustic Ceiling is being procured

Comments

comments