Brief History of All Saints’ Cathedral

 Founded in 1912 as a chaplaincy of a European colonial hospital, All Saints’ Cathedral, Kampala (ASCK) has, through the times grown and attained the status of a Cathedral for the Archbishop of the Church of Uganda. The Cathedral is governed by the Canons of Church of Uganda and the ASCK Constitution of 1975. The Cathedral is also led by the Provost who is assisted by a team of clergy and lay staff. At ASCK, various Ministries, Programmes and Fellowships are run by committees composed of mostly volunteer Christians who are parishioners.

Our Vision: A Christ centered, caring church, meeting the dynamic needs of the community

 

Need for a new Cathedral

All Saints’ Building project actively started in 2004; following a needs assessment survey which ranked the need for adequate worship space as prime. All Saints’ Cathedral Building Committee (ACP) was appointed in 2009 as the successor committee of the Archbishop’s Building Committee (ABC). It was mandated to spearhead the building of a new Diocesan Cathedral in order to address the need for worship space and other attendant cathedral facilities. This in addition entailed acquiring additional land, master planning the available land and managing the extensive building project and its ensuing sub-projects.

 

Building Timelines/Historical Milestones

The All Saints’ Cathedral Building Project (ACP) Team has been steering the project on behalf of the Cathedral Council, in collaboration with the Cathedral Management since 2009. The broad assignment is to build a Cathedral that will address the need for more worship space. Other indispensable objectives are: acquiring additional land, master planning the available Cathedral land, and managing this extensive project and its ensuing sub-projects. The following are major highlights of the project progress mainly in the recent past:

Apr 2004              Formation of ABC

May 2008             Plot 4 secured

Mar 2009            Formation of ACP Team

Jul 2009                Design Consultant procured

Sep 2009             Design Process commenced

Nov 2009             Ground breaking ceremony held

Mar 2010             Design Concept / Scheme approved

Jul 2010                Grand Fundraising held

Aug 2010              Contractor procured

Sept 2010           KCC Approval obtained

Dec 2010              Supervision Consultant procured

Dec 2010              Construction works commence

Feb 2011              Laying of Foundation Stone

Sep 2011              Grand Fundraising

Mar 2012             Launch of 2012 Fundraising strategies

December 2015 Clearance of the loan with the bank.