The ACP Team is grateful to God for His faithfulness for the Cathedral Building project, now in Phase 3 which is the completion phase. The new Sanctuary is fully plastered internally and external works for storm water drainage, paving, boundary fencing and gates are done. Project completion for all works and installations is anticipated by the end of the year 2023.

By end of September 2023 – all Interior works for the Sanctuary will be completed – fully closed, Acoustic Ceiling, floor finishes, all internal finishes and with electro-mechanical installations.

The above roadmap heavily depends on how fast we can close the funding gap estimated over UGX 5.5 Billion of which we have so far collected 957,755,091/=. The balance now is 4,542,244,909/=. Brethren, the finishing line is near, do not despair!

We encourage you to continue to: Pray, Participate, Provide and (mobilize) Partners for this great work as we honor God. Thank you, for your continued support.

FINANCIAL STATUS
ACP Summary of Collections for 17th April to 24th April, 2023.

INCOME DESCRIPTION
8am service UGX. 1,482,900/=
10:00am service UGX. 13,656,400/= USD 20
12:00 Noon serviceUGX. 2,518,400/=
Office/Walk in CollectionsUGX. 1,200,000/=
Total CollectionsUGX. 18,857,700/= USD 20;

 

TECHNICAL STATUS
The project is in the hands of Consultants and the site remains under restricted access.
Works on Vertical Windows (Lot 8A) is on-going under M/s Hebron Investments Limited.

After two unsuccessful procurement cycles, the Works Contract for Completion Works for Interiors to the new Sanctuary was finally signed on 19th December 2022.

Contractor is Seyani International Company Limited
• Contract Sum is UGX 6,965,469,955= which includes VAT amounting to UGX 1,062,529,315=
• Scope of Works covers – Floor finishes (Lot 6), Closures – Doors and Railings (Lot 7), Acoustic Ceiling (Lot 9), Electrical / ICT installations (Lot 10) and Mechanical installations (Lot 11)
• Contract duration – 9 months
• Time frame – Commencement date – 04th January 2023 while the planned Completion date is 15th September 2023.

To contribute to the building of the Cathedral, you can deposit money directly on our bank accounts (A/c Name: All saints Cathedral ACP Fund; 01273550356324 – DFCU; 0341186188- Absa Bank; KCB-All Saints Cathedral Kampala (ACP); A/c No: 2290717762)
We continue to trust and believe in our God who has brought us this far!