The ACP Team is grateful to God for His faithfulness for the Cathedral Building project, now in Phase 3 which is the completion phase. Over the 2 year COVID-19 pandemic and lockdown season, the new Sanctuary was fully plastered internally and external works for storm water drainage, paving, boundary fencing and gates were done. Thank you, for your continued support.

Project completion for all works and installations is anticipated by the end of the year 2023 as follows:

a) By end of August 2023 – all Interior works for the Sanctuary will be completed – fully closed, Acoustic Ceiling, floor finishes, all internal finishes and with electro-mechanical installations.

b) By end of December 2023 – all Exterior works – Walls (slanting, bell tower and every wall surface) to be cladded, pending offices (on lower ground) and any other pending works to be completed.

The above roadmap heavily depends on how fast we can close the funding gap estimated over 8 Billion. Brethren, the finishing line is near, do not despair! We encourage you to continue to: Pray, Participate, Provide and (mobilize) Partners for this great work as we honor God.

TECHNICAL STATUS

The project is in the hands of Consultants and the site remains under restricted access.

The key challenge still hindering continuation of full-scale site works is delayed acquisi-

tion of the Building Permit required from KCCA pending resolution of plot 4 ownership.

Currently, the following activities are on-going

  • Lot 6A – Floor Finishes in Terrazzo (for high traffic and wet areas), practically completed pending thematic landings and final grinding/polishing to be done at a later stage of site completion. Terrazzo Masters will proceed to do all floor finishes for the entire Bell Tower.

  • Lot 8A – Windows to Vertical Walls – 80% complete.

  • Procurement for Completion Works for Interiors – Comprising Floor finishes (Lot 6), Closures – Doors and Railings (Lot 7), Acoustic Ceiling (Lot 9), Electro-Mechanical Lots 10/11) – a single procurement cycle was initiated under a Restricted Tendering Method, to save time.

FINANCIAL STATUS

ACP Summary of collections for 5th – 14th December, 2022

8am service UGX. 2,802,000/= ; USD $ 100
10:00am service UGX. 7,099,700/=; USD $ 1,100; Rwanda Francs 300; Kshs 100;
12:00 Noon serviceUGX. 3,143,400/=;
Office/Walk in CollectionsUGX. 4,400,000/=;
Total CollectionsUGX. 17,445,100/= USD $ 1,100; Rwanda Francs 300; Kshs 100;

Cash fixed for Selected Works –1,913,048,915/=

Cash at hand as at 14th December 2022 –947,914,437/=

Funds Mobilisation- ‘‘Kola Wotula’’ Ceiling Campaign 2022

The Kola Wotula Ceiling Campaign commenced in March 2022 and is intended to organize us in smaller units to raise 1,000 individuals/families/fellowships/home cells each contributing at least Ugx 1,500,000 towards the cost of the acoustic ceiling.

The indicative estimate targeted for Ceiling works is Ugx 2.3billion as tendered.The total collections received as at 14th December, 2022 is UGX 490,085,711/= (Four hundred ninety million eighty five thou sand seven hundred eleven shillings only)

We appeal to you to mobilize your families and friends to contribute to this on-going campaign.

To contribute to the building of the Cathe- dral, you can deposit money directly on our bank accounts (A/c Name: All saints Cathedral ACP Fund; 01273550356324 –DFCU; 0341186188- Absa Bank; KCB-All Saints Cathedral Kampala (ACP); A/c No: 2290717762)
We continue to trust and believe in our God who has brought us this far!