Phase 3 of the project includes civil works finshes, closures, fittings, equipment Installations and furnishing.
During this year 2020, we will focus on the Sanctuary interiors and associated building services. In 2021, the Sanctuary Exteriors, Bell Tower and Offices (lower ground) will be done. Furnishing and Equipment installations may be achieved at any time, as the Lord provides the resources.
ACP Team is grateful for all your contributions to the project. We encourage you to continue to: Pray, Participate, Provide and (mobilise) Partners for this great work as you honour God.

A. Financial Status:
ACP Summary of collections for January and February 2020

Week 1 (February 2020)Week 2 (February 2020)Week 3 (February 2020)
7:30amUgx. 4,249,200; USD $ 4Ugx. 1,633,100; USD $ 101Ugx. 1,502,900
9:30amUgx. 8,186,800; USD $ 520Ugx. 2,647,100; USD $ 200Ugx. 2,791,500
11:30amUgx. 4,724,700Ugx. 2,284,600Ugx. 1,536,700
3pm (Safe Box)Ugx. 181,000; Ugx. 150,100
Safe Box (Other Collections)Ugx. 1,895,300; USD $20Ugx. 4,848,400; USD $ 1
ACP Office & Tent CollectionUgx. 14,806,900;Ugx. 4,982,500Ugx. 12,982,000
TOTAL COLLECTIONSUgx. 33,862,900; USD $ 540Ugx. 16,546,100; USD $ 302Ugx. 18,723,100

Phase III, Lot 1 collections- UGX 1,252,110,703

B. Technical Status
Transition works into phase 3 have commenced. The site will be under restricted access. Some of the identified transition works will be completed in time for Installation of the incoming Archbishop/ Bishop of the Diocese of Kampala.
Transition Works being executed include:
• Altar area works – Wall plastering and anti-glare to external windows;
• Railings – permanent to galleries, temporary to stair cases and balconies;
• Block work – Wall in-fills;
• External Works – earthworks, levelling, retaining walls, ramps, laying motorable pavers, alternate access on Lugard road to drop-off area and boundary walling between our plot 6 and the lower side of Nakasero road.

Terms of Reference for Continuation of Consultancy services have been issued. It is anticipated that the same Consltants and Interior designers will be re-engaged for phase 3 by the end of February 2020.

The interim schedule is as follows:
• February 2020 – Transition works and re-engagement of Consultants.
• March 2020 – Transition works and Procurement of Main Contractor and Specialist sub-contractors.
• April 2020 – Continuation of Sanctuary Interiors Works

C. Funds Mobilisation:
Thanks go to all the regular givers to ACP through: On going
celebrations thanksgiving, Gideon commitments, regular Sunday collections, Fellowship and Group contributions, individual and family giving, one-off giving, Diaspora giving as well as buying of ACP branded Souvenirs.

To contribute to the building of the Cathedral, you can deposit money directly on our Bank Accounts [A/c Name: All Saints Cathedral ACP Fund; 01273550356324 – DFCU; 0341186188 – Barclays; KCB All Saints Cathedral Kampala [ACP]; A/c No:2290717762] and Mobile Money using the details on the white ACP envelopes.

You can also contribute through ACP office, Cathedral Accounts office, Tent and the purple bag.
Thank you and Blessed Year 2020
ACP Team

Comments

comments