The All Saints’ Cathedral Building Project [ACP] is a special project of the Cathedral.

The current Sanctuary has been expanded three times in its life and now fills to capacity with an overflow of people occupying three large tents introduced on the Church compound over 20 years ago. The Cathedral project has lasted over 15 years and has so far gone through the hands of three (3) Archbishops and five (5) Provosts. This makes the parishioners eager to see the new Cathedral completed.

The new 5000-seater Cathedral designed in 2010 is being implemented on limited land space on Nakasero Hill, in Kampala City, as a storied complex in 3 phases:

  • Phase 1 covered the basement parking for 150 cars and new Cathedral Offices lay out. This was completed in 2012 and obligations were settled in 2015;
  • Phase 2 covered the Super Structure of the Sanctuary to achieve a roofed building in October 2019.
  • Phase 3: has commenced and will include Finishes, Closures, Fittings, Equipment Installations and Furnishing.

During this year 2020, we will focus on the Sanctuary interiors and associated building services. In 2021, the Sanctuary Exterior, Bell Tower and Offices [lower ground] will be done. Furnishing and Equipment Installations may be achieved at any time, as the Lord provides the resources.

The projected cost for the Sanctuary Interiors, Closures and Sanitary facilities is estimated at UGX 7.5 Billion to cover Works, Consultancy services and Taxes. The Archbishop, Provost and ACP Team are grateful for all your contributions to the project.
We encourage you to continue to: Pray, Participate, Provide and [mobilise] Partners for this great work as you honour God.

A. Financial Status:
ACP Summary of collections for March 2020

Week 1 (March 2020)Week 2 (March 2020)
7:30amUgx. 5,871,500; Ugx. 4,841,600
9:30amUgx. 6,551,000; USD $ 100Ugx. 6,881,800; USD $1
11:30amUgx. 2,797,700;
3pm (Safe Box)Ugx. 183,000; USD $ 100Ugx. 31,500; USD $ 1
Safe Box (Other Collections)Ugx. 4,608,200; USD $ 100Ugx. 2,293,500;
ACP Office & Tent CollectionUgx. 5,946,100Ugx. 2,250,000
Interest on Fixed DepositUgx. 14,438,356
TOTAL COLLECTIONSUgx. 25,958,100; USD $ 300Ugx. 28,511,756; USD $ 2

Phase III, Lot 1 collections: UGX 1,341,656,734

Transitional works paid: UGX 134,479,186

Balance, Lot 1: UGX 1,209,479,548

B: Technical Status
Phase 3 works have commenced and hence the site will remain under restricted access. Transition Works ongoing include: Wall plastering,
Railings, Block wall in-fills and External Works i.e earthworks, levelling, retaining walls, Ramps, Paving and Boundary Fencing.
The interim schedule is as follows:

  • March, 2020 – Transition works and re-engagement of Consultants and Interior designers.
  • April, 2020 – Transition works and Procurement of Main Contractor and Specialist sub-contractors.
  • May, 2020 – Continuation of Sanctuary Interiors Works.


C. Funds Mobilisation:
Thanks go to all the regular givers to ACP through: On going celebrations thanksgiving, Gideon commitments, regular Sunday
collections, Fellowship and Group contributions, individual and family giving, one-off giving, Diaspora giving as well as buying of ACP
branded Souvenirs.
To contribute to the building of the Cathedral, you can deposit money directly on our Bank Accounts [A/c Name: All Saints Cathedral ACP
Fund; 01273550356324 – DFCU; 0341186188 – Barclays; KCB- All Saints Cathedral Kampala [ACP]; A/c No:2290717762] and
Mobile Money using the details on the white ACP envelopes.

You can also contribute through ACP office, Cathedral Accounts office, Tent and the purple bag.
Thank you and Blessed Year 2020
ACP Team