ACP Update for Sunday 22nd November 2020

The ACP Team joins all brethren to thank God for His faithfulness and how He has sustained the living church through the tough lock-down season. The year 2020 is being optimized through Transition Works in small lots, while Large scale scope of Works are anticipated in 2021, notwithstanding the continuing effect of the Covid-19 pandemic[…]

The ACP Team continues to thank God for His faithfulness for the Cathedral Building project through the tough lock-down season. Phase 3 works are ongoing and hence the site remains under restricted access. This year 2020 is being optimized through Transition Works in small lots, despite the continuing effect of the Covid-19 pandemic on construction[…]

ACP Update for Sunday 11th October 2020

The ACP Team joins all brethren to thank God for His faithfulness and how He has sustained the living church through the tough lock-down season. The year 2020 is being optimized through Transition Works in small lots, while Large scale scope of Works are anticipated in 2021, notwithstanding the continuing effect of the Covid-19 pandemic[…]

ACP Update (Sunday 22nd March 2020)

The All Saints’ Cathedral Building Project (ACP) has lasted over 15 years and has so far gone through the hands of three (3) Archbishops and five (5) Provosts. His Grace, the Most Rev. Dr. Stephen Samuel Kaziimba Mugalu has indicated completion of the Cathedral as point no.1, in the Bishop’s charge. The Archbishop has also[…]

ACP Update for Sunday 15th March 2020

  The All Saints’ Cathedral Building Project [ACP] is a special project of the Cathedral. The current Sanctuary has been expanded three times in its life and now fills to capacity with an overflow of people occupying three large tents introduced on the Church compound over 20 years ago. The Cathedral project has lasted over[…]

ACP Updates (Sunday 8th March 2020)

The All Saints’ Cathedral Building Project [ACP] is a special project of the Cathedral. The current Sanctuary has been expanded three times in its life and now fills to capacity with an overflow of people occupying three large tents introduced on the Church compound over 20 years ago. The Cathedral project has lasted over 15[…]

ACP Update (Sunday 1st March 2020)

Phase 3 of the project includes civil works finishes, closures, fittings, equipment Installations and furnishing. During this year 2020, we will focus on the Sanctuary interiors and associated building services. In 2021, the Sanctuary Exteriors, Bell Tower and Offices (lower ground) will be done. Furnishing and Equipment installations may be achieved at any time, as[…]

ACP Updates (Sunday 23rd February 2020)

Phase 3 of the project includes civil works finshes, closures, fittings, equipment Installations and furnishing. During this year 2020, we will focus on the Sanctuary interiors and associated building services. In 2021, the Sanctuary Exteriors, Bell Tower and Offices (lower ground) will be done. Furnishing and Equipment installations may be achieved at any time, as[…]

ACP Updates (Sunday 16th February 2020)

Phase 3 of the project includes civil works finshes, closures, fittings, equip- ment Installations and furnishing. During this year 2020, we will focus on the Sanctuary interiors and associated building services. In 2021, the Sanctuary Exteriors, Bell Tower and Offices (lower ground) will be done. Furnishing and Equipment installations may be achieved at any time,[…]

ACP Update (Sunday 9th February 2020)

Phase 3 of the project includes civil works finishes, closures, fittings, equipment Installations and furnishing. During this year 2020, we will focus on the Sanctuary interiors and associated building services. In 2021, the Sanctuary Exteriors, Bell Tower and Offices (lower ground) will be done. Furnishing and Equipment installations may be achieved at any time, as[…]